In qualitative risk analysis, the project team sometimes uses a numeric scale and a color coding system assigning red, yellow and green to a pre-determined value range. This color coding system breaks the risks into groups requiring different level of attention. Green risks are those that (selected the best answer).
Options
A.Are of least concern
B.Can be ignored
C.Should be closely monitored
D.Require more attention
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
In this question, we are evaluating what green risks signify in a qualitative risk analysis color-coding scheme that uses red, yellow, and green to categorize risk levels.
Option 1: 'Are of least concern' — This aligns with the common interpretation that green-coded risks are the lowest priority or least concerning, indic......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Which risk characteristics are evaluated during the qualitative risk analysis?
ISO 31000 based risk analysis is
Anita is working with her team and SMEs to prioritize identified risks for further analysis. They decide to use a five-point scale of very low (VL), low (L), medium (M), high (H), and very high (VH) to assess the likelihood and impact of risk events. This process may be best described as
Which of the following tools and techniques are mostly recommended for qualitative risk analysis? (Select all that applies).
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!