Single choice
Why do network diagrams typically precede Gantt charts in complex projects?
Options
A.They show logical dependencies before calendar dates
B.They show progress over time
C.They are easier for executives to read
D.They replace the need for scheduling tools
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
When evaluating why network diagrams typically precede Gantt charts in complex projects, several points come into play.
Option 1: 'They show logical dependencies before calendar dates' is accurate because network diagrams (like PERT/CPM or activity-on-node/arrow diagrams) map out the sequence and relationshi......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
Question11 You have recently been assigned as the manager of a highly critical national project which should be finished in a very short period of time compared to the similar projects. After developing the first draft of the project network diagram you see that the project cannot be finished on time. If the network diagram cannot be changed anymore and you have extra human resources, what would be the best approach?Select one alternative: Fast tracking Risk analysis Leveling the resources Crashing ResetMaximum marks: 2