What is a graphical network model that depicts a project’s tasks and the relationships between them?
Options
A.Gantt chart
B.Critical path
C.Dependency
D.PERT chart
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
The prompt asks for a graphical network model that shows a project’s tasks and how they relate to one another.
Option 1: Gantt chart. This is primarily a horizontal bar chart illustrating task duration and schedule over time, not a netwo......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Why do network diagrams typically precede Gantt charts in complex projects?
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2