Questions
Single choice
What is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date?
Options
A.Kill switch
B.PERT
C.Slack
D.Project charter
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
The question asks about a concept in project scheduling that describes how long an activity can be delayed without impacting downstream tasks or the overall finish date.
Option 1: Kill switch. This term is typically used to describe ......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
An activity with positive slack can be delayed without impacting the overall project completion time.
Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.
Why do network diagrams typically precede Gantt charts in complex projects?
Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!