Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2

Options
A.By finishing the tasks with free floats sooner.
B.By delaying the tasks with free float.
C.By assigning free floats to the tasks in critical path to put the pressure off from resources.
D.By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
To tackle this question, I’ll evaluate what free float means and how it can influence the project schedule. Option 1: 'By finishing the tasks with free floats sooner.' While finishing tasks earlier can sometimes help, free float specifically refers to the flexibility to delay a task without affecting successor start times. Finishing earlier does not inherently shorten the project unless it frees up ......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!