Question11 You have recently been assigned as the manager of a highly critical national project which should be finished in a very short period of time compared to the similar projects. After developing the first draft of the project network diagram you see that the project cannot be finished on time. If the network diagram cannot be changed anymore and you have extra human resources, what would be the best approach?Select one alternative: Fast tracking Risk analysis Leveling the resources Crashing ResetMaximum marks: 2

Options
A.Fast tracking
B.Risk analysis
C.Leveling the resources
D.Crashing
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
First, let's restate the scenario and the options to ensure clarity about what we are evaluating. - Scenario: You’re managing a highly critical national project with a very tight deadline. The network diagram (project schedule) cannot be changed anymore, and you have extra human resources available. The question asks for the best approach given these constraints. - Options: Fast tracking, Risk analysis, Leveling the resources, Crashing. Option 1: Fast tracking. This technique increases project speed by performing activities in parallel that were originally planned in sequence. However, fast tracking often introduces more risk and ......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!