Assume that an activity can begin only after two other activities are completed. If the earliest completion time of one predecessor is twenty days, and the earliest completion time of the other predecessor is seventeen days, then the earliest start time of this activity must be twenty days.

Options
A.True
B.False
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
In this scheduling scenario, an activity that can begin only after two predecessors is constrained by the later of the two finish times, because both must be completed before starting. Option True:......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!