BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

Single choice

Why is 'starting with dates' instead of building a WBS first considered risky?

Options
A.It delays execution start
B.It hides real dependencies and logic under arbitrary deadlines
C.Dates reduce accountability for tasks
D.It inflates cost estimates by default
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
When you start with dates rather than a Work Breakdown Structure (WBS), the project planning dynamics shift in a few problematic ways. Option 1: 'It delays execution start' — While early dates might push activities, the core issue isn’t just delaying work; it’s that schedules built from dates can prematurely anchor work without understanding dependencies, making subsequent adjustment......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!