ACCT10001_2025_SM1 Tutorial Preparation Quiz Topic 9

Single choice

All of these are possible reasons for a favourable materials cost variance, except:

Options
A.an overestimation of materials usage in the original budget.
B.cost savings on the purchase of materials.
C.the more efficient use of materials.
D.an increase in production above budget.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
Question restatement: The prompt asks which item is NOT a possible reason for a favourable materials cost variance. The four options are presented for evaluation. Option 1: 'an overestimation of materials usage in the original budget.' If the budget anticipated more materials would be used than actually were used, the actual cost would be lower than the budgeted co......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!