Question at position 4 When a supply chain planner talks about using the BOM to do an MRP Explosion, they are talking about?The demand for final products that are affected by trends, seasonal patterns, and general market conditionsRelating gross requirements for a component part to the planned order releases of the parent itemWhen the supplier will use Value Analysis and disassemble the part to see how it's madeThe process of converting a parent item’s planned order releases into component gross requirementsClear my selection
Options
A.The demand for final products that are affected by trends, seasonal patterns, and general market conditions
B.Relating gross requirements for a component part to the planned order releases of the parent item
C.When the supplier will use Value Analysis and disassemble the part to see how it's made
D.The process of converting a parent item’s planned order releases into component gross requirements
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
In this question, we’re being asked to identify what MRP explosion entails when someone discusses using the BOM (bill of materials) for this purpose.
Option 1: 'The demand for final products that are affected by trends, seasonal patterns, and general market conditions' This describes external demand influences or forecasting considerations for finished goods, not the internal translation of orders into component......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
If a parent product requires 2 units of Component A, and MPS releases 200 parents, the gross requirement for Component A is:
If projected on-hand = ending inventory of last week + receipts – gross requirements, then a negative result means:
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!