Which of the following is not needed when creating a Gantt chart?

Options
A.A dimension (a task, event, or activity).
B.The person assigned to the dimension.
C.Start dates for tasks.
D.A measure for time duration.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
When constructing a Gantt chart, you map out the sequence and timing of tasks, so start by identifying what elements are essential for scheduling and visualization. Option A: A dimension (a task, event, or activity). This is fundamentally necessary because the chart is organized around disc......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!