Single choice
A Gantt workstation chart shows:
Options
A.The progress of each job through all work centers
B.The project budget and costs
C.The schedule of jobs assigned to specific workstations
D.The resource requirements per week
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
Examining what a Gantt workstation chart represents helps distinguish among the options.
Option 1: 'The progress of each job through all work centers.' This sounds like a line-by-line tracking of workflow across centers, which is more characteristic of a pr......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
What is a simple bar chart that depicts project tasks against a calendar?
A(n) Blank ______ chart is a simple bar chart that lists project tasks vertically against the project’s time frame, listed horizontally.
What is a simple bar chart that lists project tasks vertically against the project’s time frame, listed horizontally?
To keep track of how a decision is implemented, a _______ can be useful.