Your team estimates that a new feature will take 3 weeks based on similar past projects. However, halfway through, a key dependency is delayed, and integration takes an extra two weeks. Your manager asks why the estimate was so far off. What was most likely missing from the team’s estimation process?
Options
A.Planning poker
B.Accurate story points
C.A Gantt chart
D.Developer time tracking
E.Buffering for uncertainty and external risk
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
The scenario describes a project estimate that was later invalidated by an outside factor—a key dependency delaying and pushing integration by two weeks. This points to a gap in anticipating uncertainty and external risks rather than purely internal planning accuracy.
Option 1: 'Planning poker' — Planning poker is a collaborative estimation technique used to assign effort or size......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
In a consumer society, many adults channel creativity into buying things
Economic stress and unpredictable times have resulted in a booming industry for self-help products
People born without creativity never can develop it
A product has a selling price of $20, a contribution margin ratio of 40% and fixed cost of $120,000. To make a profit of $30,000. The number of units that must be sold is: Type the number without $ and a comma. Eg: 20000
More Practical Tools for International Students
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!