Single choice
Why can CPI alone give a misleading picture of project health?
Options
A.It ignores schedule pressure and timing of work
B.It ignores scope
C.It ignores cost performance
D.It changes over time
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
Consider what CPI is and what it measures in project control.
Option 1: 'It ignores schedule pressure and timing of work' — this is true. CPI calculates cost performance by comparing earned value to actual cost, focusing on cost efficiency, not on when work is performed or......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. You are ahead of schedule. Your project is running according to the budget. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2