Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. Your project is running according to the budget. You are ahead of schedule. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2

Options
A.The project is getting 87 cents out of each dollar spent.
B.Your project is running according to the budget.
C.You are ahead of schedule.
D.The progress of your project is only 87% of what it is planned, so you are behind the schedule.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
To interpret the Schedule Performance Index (SPI), we recall that SPI = EV / PV, where EV is earned value and PV is planned value. An SPI of 1.0 indicates schedule performance exactly as planned. Values below 1.0 mean the project is progressing more slowly than planned, while values above 1.0 indicate ahead-of-schedule performance. Option 1......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!