Questions
CVEN9731 Project Management Framework - 2025 T3
Single choice
You are managing a project with a one-year duration and a budget at completion (BAC) of $ 100,000. After 6 months, the project is 40% complete and the actual cost (AC) is $40,000. Consider a linear project progress inn this case. Which one of the following statements is correct?

View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
Start by identifying the key values and applying earned value concepts. EV (earned value) = percent complete × BAC = 0.40 × 100,000 = 40,000. AC (actual cost) = 40,000. PV (planned value) at 6 months for a linear, one-year project = (6/12) × BAC = 0.5 × 100,000 = 50,000.
Option a: 'The project is behind the schedule ......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Why can CPI alone give a misleading picture of project health?
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!