Questions
Questions

CVEN9731 Project Management Framework - 2025 T3

Single choice

You are managing a project with a one-year duration and a budget at completion (BAC) of $ 100,000. After 6 months, the project is 40% complete and the actual cost (AC) is $40,000. Consider a linear project progress inn this case. Which one of the following statements is correct?

Question Image
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
Start by identifying the key values and applying earned value concepts. EV (earned value) = percent complete × BAC = 0.40 × 100,000 = 40,000. AC (actual cost) = 40,000. PV (planned value) at 6 months for a linear, one-year project = (6/12) × BAC = 0.5 × 100,000 = 50,000. Option a: 'The project is behind the schedule ......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!