PMGT5820 (all) Week 7 Knowledge Test - Evaluate and manage project progress

Single choice

Figure 1. Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 2024) WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Consider the project performance report presented in figure 1. What valid conclusion can you draw regarding the project cost performance as of October 31, 2024?

Options
A.The project is $8,000 over budget
B.The project is $18,000 over budget
C.The project is on budget
D.The project is $26,000 under budget
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
To start, I will restate the core data from the report so we can compare planned, earned, and actual costs accurately. - Planned Value (PV) totals: 342,000 - Earned Value (EV) totals: 316,000 - Actual Cost (AC) totals: 324,000 With these numbers, we can evaluate each answer option by computing the key cost-performance indicators and variances. Option 1: "The project is $8,000 over budget" - The cost variance (CV) is EV minus AC: 316,000 − 324,000 = −8,000. A negative......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!