Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
Options
A.Ahead of schedule but over budget
B.Performance cannot be assessed
C.Behind schedule and over budget
D.Over budget but efficient
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
To tackle this question, I’ll evaluate what CPI and SPI indicate in Earned Value Management and then test each answer choice against those indicators.
Option 1: 'Ahead of schedule but over budget' would require SPI > 1 (better schedule performance) and CPI < 1 (cost overrun). Since the question states both CP......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Why can CPI alone give a misleading picture of project health?
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. You are ahead of schedule. Your project is running according to the budget. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!