BU.300.620.51.FA25 Managing Complex Projects – Final Exam (35Q)

Single choice

Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?

Options
A.EAC = BAC / CPI
B.EAC = AC + (BAC − EV) / CPI
C.EAC = AC + (BAC − EV) / (CPI × SPI)
D.EAC = EV + AC − PV
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
Topic context: Earned Value Management (EVM) in project scheduling and cost forecasting. The question asks which EAC (Estimate at Completion) formula is MOST realistic given CPI < 1 and SPI < 1, with schedule pressure causing overtime. Option A: 'EAC = BAC / CPI' — This formula isolates cost performance factor only, duplicating consideration of CPI but ignoring schedule performance (SPI) and work scope progression. If SPI is < 1, more work remains than earned value would indicate, so using only CPI would under-adjust the completi......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!