Questions
Questions

PMGT5889 (NE) Online Quiz

Single choice

Your project status can be presented with the diagram: What is the status of your project? Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC  

Options
A.Ahead of schedule, under budget
B.Behind schedule, over budget
C.Behind schedule, under budget
D.Ahead of schedule, over budget
Question Image
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
First, restating the scenario helps set the stage: we’re given an Earned Value Management (EVM) framework with how SV and CV are defined, and the question asks which status option best matches the typical interpretation of those variances. Option 1: 'Ahead of schedule, under budget' would imply a positive schedule variance (SV > 0) meaning EV > PV, indicating the earned value is ahead of the planned value. It would also imply a negative cost variance (CV < 0) meaning EV < AC, i.e., actual costs exceed the earned value, which ......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment

Your project status can be presented with the following diagram: Match the values presented in this graph with the corresponding Earned Value Analysis indicators. Formulas: EVA Component Formula Planned value (PV) N/A Earned value (EV) N/A Actual cost (AC) N/A Budget at completion (BAC) N/A Schedule variance (SV) SV = EV – PV Cost variance (CV) CV = EV- AC Estimated final duration PlannedProjectDuration / SPI % Complete %Complete = (EV/BAC) x 100 Schedule performance index (SPI) SPI  = EV/PV Cost performance index (CPI) CPI = EV/AC Estimate at completion (EAC) – final cost Future work will be accomplished at the planned rate: Both CPI and SPI influence the remaining work: CPI is expected to be the same for the remainder of the project:   EAC = AC + BAC – EV  EAC = AC + [(BAC-EV)/(CPIxSPI)]  EAC = BAC/CPI Estimate to complete (ETC) ETC = EAC – AC Variance at Completion (VAC) VAC = BAC-EAC 1: Actual Cost (AC) 2: Planned Value (PV) 3: Earned Value (EV) 4: Original Budget (BAC) 5: Schedule Performance Index (SPI) 6: Cost Performance Index (CPI) 7: Schedule Variance (SV) - money 8: Cost Variance (CV) 9: Project duration (months) 10: Months that project is behind/ahead of schedule at the moment

In a consumer society, many adults channel creativity into buying things

Economic stress and unpredictable times have resulted in a booming industry for self-help products

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!