4510_DESST_3514 Wk7 Lecture: Cost & Program

Single choice

2. According to the cost influence curve, when is it most cost-effective to make design changes?

Options
A.A. During construction
B.B. During the documentation stage
C.C. During the tender process
D.D. During the concept and early design stages
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
The question asks when it is most cost-effective to make design changes according to the cost influence curve. Option A: During construction. Making changes during construction tends to be very expensive because it requires altering already-built elements, disrupting on-site work, potential rework, ......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!