Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2

Options
A.It might affect activity I, so reject the proposal
B.This does not have any effect on the critical path, so reject the proposal
C.This will help all of the delay to be recovered, so accept the proposal
D.This will help you spend less resources, so accept the proposal
Question Image
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
To tackle this question, I’ll walk through each option and evaluate its claim in the context of project scheduling and critical path concepts. Option 1: 'It might affect activity I, so reject the proposal' This option suggests that changing the sequence by running H concurrently with G could impact activity I. Without a detailed network diagram showing dependencies, it’s risky to assume I is affected. If I is not on the critical path or if its predecessors aren’t constrained by G or H in a way that creates a delay, the impact may be limited. However, the statement is speculative and asserts a def......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!