Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2

Options
A.By delaying the tasks with free float.
B.By finishing the tasks with free floats sooner.
C.By assigning free floats to the tasks in critical path to put the pressure off from resources.
D.By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
Question restatement: The prompt asks how free float can be used to shorten a project schedule, selecting the correct alternative. Option 1: By delaying the tasks with free float. This is not a method to shorten the overall project duration. Free float represents the amount of time a non-critical task can be delayed without impacting the project end date, but delaying these tasks does not compress th......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!