Questions
Homework:Ch 08 Homework
Multiple fill-in-the-blank
Part 1The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: [table] | Copy to Clipboard | | + [/table] [table] Activity | Activity Time (days) | Immediate Predecessor(s) A | 66 | long dash— B | 11 | A C | 33 | A D | 33 | B, C E | 44 | D F | 66 | E G | 55 | E [/table]Part 2a. Choose the correct network diagram for this project.Part 3 A. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1, circle B 1 connects to circle C 3 and to circle D 3, circle C 3 also connects to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6 and to circle G 5, and circles F 6 and G 5 both connect to rectangle Finish. B. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1 and to circle C 3, circles B 1 and C 3 connect to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6, circle F 6 connects to circle G 5 and to rectangle Finish, and circle G 5 also connects to rectangle Finish. C. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1, circle B 1 connects to circle C 3 and to circle D 3, circle C 3 also connects to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6, circle F 6 connects to circle G 5 and to rectangle Finish, and circle G 5 also connects to rectangle Finish. D. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1 and to circle C 3, circles B 1 and C 3 connect to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6 and to circle G 5, and circles F 6 and G 5 both connect to rectangle Finish. Your answer is correct. Part 4b. Determine the critical path and project duration.The critical path is path [input] ▼ empty selection and the project duration is [input]enter your response here days. (Enter your response as an integer.)
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
Part 1: Restating the question and options
The task presents a project with activities A through G, their immediate predecessors, and durations in days. Part 2a asks you to choose the correct network diagram that represents the given precedence relationships. Part 4b asks for the critical path and the project duration, with the answers to be provided as a path (e.g., A-B-D-E-F) and a numeric duration in days.
Options describing diagrams (A, B, C, D) differ in which arrows connect which activities and whether certain activities feed into the next steps or directly into the Finish node. Each option attempts to encode the precedence relationships listed in the table but with subtle differences in sequencing connectivity.
Option-by-option analysis
Option A:
- In Option A, Start connects to A with duration 6. Activity A then connects to B with duration 1. B connects to C (3) and to D (3). C also connects to D (3). D connects to......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Question16 Which sequence of activities forms the critical path for the following project activities.Select one alternative: Start>B>D>E>H>End Start>B>C>D>E>F>G>H>I>End Start>C>F>G>I>End Start>B>C>F>G>H>I>End ResetMaximum marks: 2
Question15 You are manager of a project and after a periodic project schedule update, the scheduler working on your team comes to you with the following list of activities. He also mentions that the project is faced with 2 weeks of delay and as a corrective action he proposes to change the sequence and perform activity H concurrent with activity G, instead of after it. What would be your reaction?Select one alternative: It might affect activity I, so reject the proposal This does not have any effect on the critical path, so reject the proposal This will help all of the delay to be recovered, so accept the proposal This will help you spend less resources, so accept the proposal ResetMaximum marks: 2
Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2
In the forward pass of the Two Pass Method, the Earliest Start Time (EST) of an activity equals the maximum of the Earliest Completion Times (ECTs) of all its immediate predecessors.
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!