Question8 You are managing a project and one of your close friends is also a manager at the client organization. During the project execution, your friend asks for changes to be made in the project scope, and with the reasoning that the changes are critical to the success of the project, he asks you to handle them on an informal basis. He argues that if you want to follow the normal change procedures you will lose considerable time. What should you do in this situation?Select one alternative: Perform the changes according to the manager’s request because they are crucial to the project success, but document them later on when the project is on track and there are no more changes to be made. Comply with the manager’s request since it is critical to the project success. Since what the manager has asked you is unethical you should refuse the changes. Explain to the manager that the change should be handled through the formal change management process and it should be documented. ResetMaximum marks: 2
Options
A.Perform the changes according to the manager’s request because they are crucial to the project success, but document them later on when the project is on track and there are no more changes to be made.
B.Comply with the manager’s request since it is critical to the project success.
C.Since what the manager has asked you is unethical you should refuse the changes.
D.Explain to the manager that the change should be handled through the formal change management process and it should be documented.
View Explanation
Verified Answer
Please login to view
Step-by-Step Analysis
When evaluating how to respond to a manager requesting informal scope changes, it’s important to weigh governance, ethics, and project control.
Option 1: 'Perform the changes according to the manager’s request because they are crucial to the project success, but document them later on when the project is on track and there are no more changes to be made.' This bypasses the formal change control pro......Login to view full explanationLog in for full answers
We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!
Similar Questions
Which of the following does NOT create a climate for change?
True or False? To increase success, it is best to organize the change process into three stages: creating a climate for change, engaging employees while transitioning into the change, and sustaining change.
The first stage in the change process is:
Which tactic for overcoming resistance to change basically assumes that the source of resistance lies in misinformation?
More Practical Tools for Students Powered by AI Study Helper
Making Your Study Simpler
Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!