Question19 In an Agile project, how does the team handle changes to requirements late in development?Select one alternative: Changes are discouraged to maintain the original project schedule and scope. Changes are welcomed and incorporated, as Agile prioritizes customer collaboration and responding to evolving needs. The team can only accept changes if they don’t affect the budget or timeline. The team conducts a formal change request process to determine the feasibility of implementing the change. ResetMaximum marks: 1

Options
A.Changes are discouraged to maintain the original project schedule and scope.
B.Changes are welcomed and incorporated, as Agile prioritizes customer collaboration and responding to evolving needs.
C.The team can only accept changes if they don’t affect the budget or timeline.
D.The team conducts a formal change request process to determine the feasibility of implementing the change.
View Explanation

View Explanation

Verified Answer
Please login to view
Step-by-Step Analysis
Question: In an Agile project, how does the team handle changes to requirements late in development? Option 1: Changes are discouraged to maintain the original project schedule and scope. - This view runs counter to Agile principles. Agile methodologies embrace change, particularly late in development, because new insights and customer feedback can deliver higher value. Treating changes as something to be disc......Login to view full explanation

Log in for full answers

We've collected over 50,000 authentic exam questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

More Practical Tools for Students Powered by AI Study Helper

Join us and instantly unlock extensive past papers & exclusive solutions to get a head start on your studies!